The Robinson School Building Committee authorized a Request for Services to procure an Owner’s Project Manager, formed a five-member selection committee and designated a procurement administrator; the committee set a compressed selection schedule tied to MSBA requirements.

The Robinson School Building Committee on Aug. 12 authorized a Request for Services (RFS) to begin procuring an Owner’s Project Manager (OPM) and appointed a five-member selection committee to evaluate proposals, the committee said at a public meeting. The committee also designated Kristen as the full-time procurement administrator responsible for the OPM procurement.

The action launches a timetable tied to Massachusetts School Building Authority (MSBA) deadlines. Committee members said respondents will submit proposals by Friday, Sept. 12, the shortlist must be completed by Sept. 18, and interviews are planned later in the month (committee members discussed a Sept. 24 interview date). The full committee penciled in a public check-in meeting for Sept. 30 to update the group on progress, while the selection subcommittee will meet earlier to complete individual evaluations and compute cumulative averages for MSBA submission.

Committee members discussed evaluation logistics and public-records protections. Town staff will create a standardized evaluation spreadsheet and matrix so each selection-panel member fills out the same scoring sheet; the committee noted that MSBA asks for a narrative of the selection process, including cumulative average scores. The committee also said the selection subcommittee must post meetings 48 hours in advance and keep minutes because the subcommittee is doing public business on behalf of the building committee.

The committee named Valerie, Lindsey, Steve, Kristen and Chris to the selection panel. Members discussed the expected workload: each panelist will review the full set of proposals independently, then the panel will meet to reconcile scores and produce a cumulative average. Committee members discussed the possibility of respondents requesting extensions but said MSBA timelines make extensions unlikely and that a firm unable to meet the three-week submission window may not be a good fit.

Other logistical items discussed: an informational meeting and site walk-through was scheduled later in the month for interested firms; questions from proposers are due by Sept. 4 with town responses by Sept. 8, and staff said questions submitted orally at the walk-through must also be submitted in writing to ensure consistent responses. Committee members agreed staff (town and school) would handle most procedural questions and that any question requiring committee direction could trigger a short, additional meeting.

Votes at a glance: the committee unanimously approved (recorded as affirmative votes by the members present) to accept the June 17 meeting minutes, to authorize the RFS for OPM services, to appoint the five-member selection panel (Valerie, Lindsey, Steve, Kristen and Chris), and to designate Kristen as the procurement administrator for the OPM procurement. The committee later voted to adjourn to executive session to consider purchase/exchange/lease or value of real property and said it would not return to public session.

Why it matters: the OPM is a required consultant in MSBA-involved school projects and will play a central role in procurement, schedule and early project feasibility analyses. The compressed schedule and MSBA documentation requirements mean the selection subcommittee must complete individual reviews and a cumulative scoring matrix on a tight timetable, and the town will retain the administrative burden of producing addenda, responses to proposer questions and the MSBA narrative.

What’s next: respondents will submit proposals by the deadline noted in the RFS; selection-panel members will complete individual evaluations and reconvene to produce cumulative scores that will be included in the MSBA submission. The committee scheduled a check-in for Sept. 30 to report progress to the full Robinson School Building Committee.