Commission approved a first construction pay application tied to the Community Development Block Grant Airport Access Road project and authorized the chair’s signature; consultants reported Phase 2 change order approval from state and commissioners deferred a separate bid decision on a parking lot that would serve SSM and future development.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Coffey County Commission approved the first pay application on Aug. 11 for the Airport Access Road project, a Community Development Block Grant (CDBG)‑funded construction effort. The motion authorized the chairman to sign a request for disbursement so the county can draw grant funds and pay the contractor.
The pay application approved covered construction work billed to date in the amount of $270,477.04; staff said the county’s budget and the CDBG grant will be used in the project ratio (consultant noted roughly a 63% CDBG / 37% county match for certain costs when professional services and administration are included). The commission approved the motion and directed the chair to sign the disbursement request to the state.
CFS engineering staff told the commission the state has approved a Phase 2 change order for the project of $722,991 to extend work to County Road and noted the project is moving forward with grading and base work. Staff said current progress included about 20% of road grading complete, staking done and base placement beginning.
In related discussion, staff presented a proposed parking lot adjacent to the new SSM (project name in packet) facility that could serve the firm’s operations and future development near the site. Commissioners asked for the design drawings, space and compaction information and a clearer cost breakdown that shows SSM’s contribution and public‑infrastructure costs before issuing a bid. Staff and engineering said they would provide full plans and share them with the commission and the SSM representative before bringing a bid authorization back; the commission did not approve the parking lot bid package at the meeting.
Why it matters: the pay application moves state CDBG dollars into county‑paid construction invoices and keeps the Airport Access Road project on schedule. The Phase 2 approval from the state expands the work scope. The proposed parking lot is a final piece of the SSM site public infrastructure but commissioners requested more details before committing to a public procurement.
What comes next: staff will submit the disbursement request to the state for processing, provide the SSM parking lot plans and cost breakdown, and return with a recommendation and bid documents if the commission chooses to proceed.