Council approves purchase of small parcel for Tidewater Reservoir replacement, authorizes $22,000 deal

5492333 · July 28, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Brookings authorized a resolution and purchase agreement to buy a small parcel from George Fitzhugh for $22,000 to site two new 74,000-gallon drinking water reservoirs; staff said the parcel was recently appraised at $10,000 but recommended purchase at $22,000 for utility use.

The Brookings City Council on July 28 adopted a resolution (recorded in the meeting packet as Resolution 25-R-1283) and authorized the city manager to execute a real estate purchase agreement with George Fitzhugh to secure a parcel for replacing the existing Tidewater Reservoir.

Staff said the existing above-ground concrete reservoir is leaking and has limited capacity and that associated water lines in the area do not provide required fire protection; the fire department currently relies on tanker support for fires in the neighborhood. The project scope includes constructing two new 74,000-gallon reservoirs and installing a new 8-inch water line to provide sufficient fire flow for the served residential area.

Staff told council the Fitzhugh property is currently covered by a small easement; the owner proposed either a 15-year easement with annual CPI-based payments or an outright purchase of the parcel for $22,000. An April 2025 appraisal listed the parcel value at $10,000; staff recommended purchasing the parcel for $22,000 because of its strategic value to the water system and to avoid future easement negotiations.

A motion to adopt Resolution 25-R-1283 and authorize the real estate purchase agreement with George Fitzhugh passed; the audio transcript records yes votes from Councilor Martin, Councilor Monfort and Mayor Hodges and the motion carried.

Staff noted the Tidewater Reservoir replacement was listed as a high-priority item in the 2014 Water Master Plan and that the overall drinking-water revolving loan fund award (received in August 2021) funded multiple water infrastructure projects, with the Tidewater Reservoir replacement being the final project associated with that loan award.