AT&T easement leaves two Lynnwood Place lots unbuildable, staff says

5456417 · July 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Development Services staff told the Planning Commission that two lots in the Lynnwood Place Unit 1 replat are currently unbuildable because of an AT&T easement; options include waiting for easement realignment or marking lots nonbuildable until relocation is negotiated.

During review of a replat for Lynnwood Place Unit 1 on July 23, Development Services staff told the City Planning Commission that two lots were deemed unbuildable because of an AT&T easement.

Commissioner Munoz asked whether the two lots were permanently excluded from development. Andrew Dimas of Development Services said the AT&T easement will be relocated: the applicant can either pause the project until the easement is realigned or record the two lots as nonbuildable for now and allow AT&T to negotiate rerouting. After AT&T completes relocation, the applicant may return to amend the plat to open those lots for development.

“That gets him into play to still build 5, 6 houses for those plotted lots, then he can come back, amend his plat once that easement has been rerouted to open those 2 lots up for development,” Dimas said.

Why it matters: the presence and routing of utility easements can determine whether lots are buildable and when development can proceed. The commission approved the replat on consent with staff recommendations.

Context/next steps: if the applicant marks the lots nonbuildable, AT&T must negotiate relocation terms before the lots can be developed; if the applicant waits, the overall plat approval remains pending the easement realignment.