New Caney ISD staff gives bond update, lists timelines for Westport, McKinney, Fort High and new schools
Summary
A district staff member briefed the New Caney ISD board on bond-funded construction and renovation projects, reporting completion targets ranging from August (school openings) to summer 2028 (large campus work) and noting a recommendation for a general contractor will be presented to the board.
Get email alerts on the Bond Construction topic
No spam. Unsubscribe anytime.
A district staff member provided a bond-projects update at the New Caney Independent School District Board of Trustees meeting, outlining progress and target dates for multiple construction and renovation projects funded by the district bond program.
The staff member said Westport Phase 2 will be ready for students when school resumes in August, with only a covered practice facility still to be built this summer. Work at McKinney High School on career and athletic facilities is largely finished and will have CTE areas ready when students return. Allen Phillips School is scheduled to open in August, and Middle School No. 6—on the Casey property—was reported as being in design and projected to open on Aug. 23 (date as stated in the meeting).
The staff update said demolition and instructional remodeling for the district's alternative school PLC behind Pine Valley is complete and that the district will present a recommendation for a general contractor for the central office to the board that evening. The transportation operations facility is projected to be completed in spring 2027, the staff member said.
Fort High School remains in design following the board's recent architect approval; planned work includes covered practice facilities, arts additions and renovations, expanded CTE spaces, turf field work and other renovations. The staff member reported a recently completed lighting project for the Fort High athletic fields and said the district expects the larger Fort High work to be wrapped up by summer 2028, given the number of moving parts.
The district also approved an architect last month for a future Elementary 13 and described a BEST program (behavioral, emotional and social training) that will establish four classrooms to support students across the district.
The staff member said bond-project details and a bond news section are available on the district website and noted that recommendations on a general contractor would come to the board that night. No formal votes on the bond projects were recorded in the open remarks summarized at the meeting.
The remarks occurred during the board meeting; the presentation emphasized construction timelines and upcoming board recommendations rather than final approvals.