Board approves single‑phase Shady Grove Park buildout using Heyday park contributions
Summary
Trustees voted to complete Shady Grove Park in one phase, authorizing use of Heyday impact fee contributions to cover a portion of the cost and avoid double mobilization.
Get email alerts on the Parks Recreation topic
No spam. Unsubscribe anytime.
The Cottage Grove Village Board on Aug. 18 approved completing Shady Grove Park in a single construction phase, using additional park development funds including $198,380 from fees collected in connection with the nearby Heyday development.
Trustee Dahl moved to proceed with the single‑phase buildout at an estimated construction cost presented to the board; Trustee Buenzo seconded and the motion carried. Staff and the park designer said completing the park in one phase reduces duplicate mobilization costs and produces a finished park that will be immediately usable by residents and future nearby development.
Why it matters: the Heyday development will generate fee‑in‑lieu funds rather than dedicated parkland. Shady Grove is the closest village park to that development; trustees agreed directing some of those fees to complete the Shady Grove plan now will avoid higher combined costs if the park were built in multiple phases.
Project details: the board reviewed a 90% design that includes a playground, looped sidewalk, a gazebo, drinking fountain and utilities. Blake, the landscape architect, explained design and placement decisions, including siting a public drinking fountain outside the shelter so it remains accessible when a shelter is reserved. The construction schedule was described as flexible; bidding may occur in fall or early next spring to achieve better pricing and contractor availability.
Next steps: staff will proceed with bidding and coordinate with the parks committee and residents on a timeline. Construction sequencing aims to minimize repeat site disturbance and allow opening of park features in the spring following completion.