The Trenton Town Council voted to award the 800 South reconstruction project to Staker Parsons, the lower of two competitive bids submitted for the COG‑funded project.
Town staff presented two bids: Staker Parsons at $245,009.83 and LeGrande Johnson at $281,658.40. Staff and the town engineer told the council the bids were not perfectly "apples to apples" in some line‑item breakdowns but that both met the project specifications; the council proceeded with the lowest responsive bid. A council member said the town was "obligated, as long as it touches all the bases, to go up the lowest bid."
The project includes culvert replacements (an 18‑inch HDPE pipe) and road base and compaction work. Staff said some engineering and geotechnical work paid by the town would count as part of the town's local match for the COG award (the award amount and match were discussed; staff reported an 8% local match requirement). Council asked that a town representative be on site during compaction work.
Separately, council members discussed a chip‑seal plan for Center Street and other roads. The county has offered to do a single chip seal plus flush (chip and fog seal) for Trenton at a county price of about $100,000 for the full project; the town's remaining COG funds for that chip‑seal project total $46,795.85. Council voted to authorize town staff to approach the county to see if the county will perform half the project this year (staff proposed a contribution in the $51,000 range to match county pricing and the town's available funds). The motion to pursue a county partnership passed.
Why it matters: Awarding the reconstruction contract advances a multi‑phase road project funded in part by a COG grant; pursuing county participation on the chip‑seal work could allow Trenton to accomplish more road surfacing this year within constrained local funding.
Council action: The council approved awarding the 800 South contract to Staker Parsons and approved staff negotiating with the county to proceed with a partial chip‑seal this season using county pricing and available COG match funds. The council also discussed project oversight and requested close coordination with the town engineer during compaction and paving operations.