Board awards multiple construction and maintenance contracts, accepts bids and sends sidewalk recommendation to council
Summary
At its April 3 meeting the Waukesha Board of Public Works approved routine payments and minutes, awarded or recommended several construction contracts (including a major clean-water plant contract), accepted low bids on multiple projects, noted a no-bid item, and forwarded a sidewalk special-charge recommendation to the City Council.
Get email alerts on the Procurement And Contracts topic
No spam. Unsubscribe anytime.
The Waukesha Board of Public Works on April 3 approved routine payments and minutes and took final action on multiple contract awards and bid recommendations for fiscal 2025 projects.
Routine approvals The board approved payments from March 20 and the minutes of the March 20 meeting. Both items were approved on unanimous voice votes after motions by Joe Piper and second by Kevin Riley.
Contract awards and bid decisions - Asphalt street repairs (Item 7A): The board accepted the low bid from Always Contractors for $203,545 and approved awarding the contract. Motion by Joe Piper; second by Kevin Riley. Vote: Cassens, Riley, Piper — all aye.
- Cemetery administration building HVAC (Item 7B): The board awarded the project to Hennis (low bid $92,410). The bid came in above the project estimate for heating/cooling equipment; staff said the ductwork and scope contributed to the cost and that carryover funds would cover the difference. Motion to approve by Joe Piper; second by Kevin Riley. Vote: unanimous.
- Clean Water Plant Phase 3 improvements (Item 7C): The board recommended moving forward with J.F. Ahern of Fond du Lac for the low bid of $18,600,000. Staff said four competitive bids were received and the project came in under budget. Motion by Kevin Riley; second by Joe Piper. Vote: unanimous.
- Prairie Home Cemetery, Autumn Garden Fountain (Item 7D): The board awarded the specialty fountain rebuild at a low bid of $45,000, which staff said exceeded an early 2024 estimate of $40,000 because additional scope was added. The project was recommended through the CIP. Motion by Joe Piper; second by Kevin Riley. Vote: unanimous.
- Gascoigne Drive and Peters Drive utility and street improvements (Item 7E): The board accepted a low bid from Leighton of $3,246,364.78 and recommended award; bid came in under budget. Motion by Joe Piper; second by Kevin Riley. Vote: unanimous.
- Badger Dry Bus Wash replacement (Item 7F): Staff reported no bids were received. The board took no award action and directed staff to re-evaluate the plans and rebid; a board member suggested coordinating with the water utility as it designs a new building to explore shared facilities.
- Schutze Building roof replacement (Item 8A): Staff recommended using the Omnia Partners public-sector contract to secure a combined low-price roofing and soffit package. The board approved contracting for a combined low price of $103,350 (including soffit alternate); funding will use CIP carryover funds and staff cautioned that decking replacement could increase final cost pending removal of existing roofing. Motion to approve by Joe Piper; second by Kevin Riley. Vote: unanimous.
Board members and staff noted reasons for acting now on several projects — chiefly that performing work while contractors are mobilized produces cost savings. Several items had only one responsive bidder; staff said low contractor interest and specialty scopes contributed to single-bid results on some projects.
Votes at a glance - Payments (4A): Approved. Motion: Joe Piper. Second: Kevin Riley. Vote: unanimous. - Minutes (4B): Approved. Motion: Joe Piper. Second: Kevin Riley. Vote: unanimous. - Silvernail Road sidewalk special charge (6A): Motion to direct staff to prepare a special charge for Sussex Lane east to University Drive — passed 2-1. (See separate article.) - 7A Asphalt street repairs: Award to Always Contractors, $203,545 — approved, unanimous. - 7B Cemetery admin HVAC: Award to Hennis, $92,410 — approved, unanimous. - 7C Clean Water Plant Phase 3: Award to J.F. Ahern, $18,600,000 — approved, unanimous. - 7D Prairie Home Cemetery fountain: Award approved, low bid $45,000 — approved, unanimous. - 7E Gascoigne/Peters Drive: Award to Leighton, $3,246,364.78 — approved, unanimous. - 7F Badger Dry Bus Wash replacement: No bids received; staff to rebid and re-evaluate. - 8A Schutze Building roof replacement: Award via Omnia Partners, $103,350 (roof + soffit alternate) — approved, unanimous.
Next steps: Awarded projects will proceed with contract execution and scheduling. The Silvernail sidewalk recommendation will be forwarded to the Common Council for final action and affected property owners will be notified of any special charge after council approval.