Developer briefs Rockville Planning Commission on potential 550-unit redevelopment at 255 Rockville Pike
Summary
At a planning commission briefing April 9, 2025, the applicant for 255 Rockville Pike presented a project-plan amendment proposing phased redevelopment—retaining a 440-space garage and adding up to 550 dwelling units or alternatively adapting the existing structure for commercial uses; no formal action was taken.
Get email alerts on the 255 Rockville Pike Redevelopment topic
No spam. Unsubscribe anytime.
On April 9, 2025, the City of Rockville Planning Commission heard a briefing on a project plan amendment and concurrent level 2 site plan for 255 Rockville Pike. Staff and the applicant described a proposal to amend the planned development (PD-RCI) to allow a phased redevelopment of the existing office structure into either a multifamily building with up to 550 units or an adaptive commercial reuse of the structure.
Kimia Zolfagarian, principal planner with Community Planning and Development Services, told the commission the site is in Planning Area 1 of the Town Center Master Plan, totals about 2.5 acres and is currently in the Planned Development — Rockville Center Incorporated zoning district with an equivalent MXTD designation. The applicant’s submittal shows a phased proposal: a first phase of roughly 300 multifamily units built over the existing parking structure and a second phase that could add about 250 units in a vertical tower with a proposed maximum height of 217 feet.
Bob Elliott, representing 255 Rockville Pike LLC, described the site as a former portion of the Rockville Mall that his firm acquired at auction about a year earlier. Elliott said the building includes a 440-space parking garage the team plans to retain and that the firm initially proposed residential redevelopment but is keeping an alternate plan for full commercial reuse to respond to rapid market changes. "We acquired this property about 1 year ago, at auction," Elliott said. He said the applicant is exploring retail configurations, single-tenant users, or a multifamily path depending on market conditions.
Staff and the applicant reviewed project history and next steps: pre-application materials were filed Dec. 20, 2024; an area meeting was held Oct. 29, 2024; the project plan amendment and site plan were filed March 7, 2025; a post-application area meeting occurred March 18; the Development Review Committee meeting is scheduled for April 24, and a mayor-and-council briefing is scheduled for May 5, 2025. Zolfagarian said the planning commission may later provide a recommendation to mayor and council and could consider a decision on the site plan application in a future proceeding.
Commissioners asked for additional detail about pedestrian and streetscape improvements along Bridal Lane and the promenade adjacent to the metro bridge and suggested potential design responses whether the project proceeds as residential or commercial. Commissioners emphasized the site’s role as a gateway from the Metro and encouraged improvements to the Rockville Pike frontage, possible sidewalk widening, protected bike lanes, storefront activation near Promenade Park, and green-roof or other sustainability measures.
Elliott acknowledged constraints tied to state highway configuration (MD-355/Bib Road) and noted ongoing coordination with the city and state about potential lane reconfiguration to widen sidewalks near Bridal Lane; he also said any significant vertical tower would be conceptual at this stage and dependent on future market conditions. No public testimony was taken because the session was a briefing, and the commission did not take action at this meeting.