Council approves change order for 2025 citywide concrete rehabilitation; ADA ramps, sidewalks prioritized

3168800 · April 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved Change Order No. 3 to Keane Concrete for the 2025 citywide concrete rehabilitation project; staff said concrete work has increased as accessibility requirements are paired with asphalt projects and the city’s annual pavement budget totals $3 million.

The Lafayette City Council on March 18 unanimously approved Change Order No. 3 to the 2025 citywide concrete rehabilitation contract with Keane Concrete Inc., city staff said, authorizing approximately $1.3 million of concrete work that pairs with the city’s asphalt rehabilitation program.

Public Works staff described the city’s pavement-management context: Lafayette has roughly 240 lane miles of roadway and an annual asphalt and concrete rehabilitation budget of about $3 million. Staff said city pavement-condition guidance (a 2020 PCI report) recommends approximately…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans