Stage 2 construction set to start in June 2025 with multi-year schedule; dewatering and dust mitigation planned
Summary
TIDA infrastructure manager outlined a June 2025 start for Stage 2 street and utility work on Treasure Island, a roughly 36-acre area with an estimated cost of $135–$150 million and about a 36-month construction window; staff described dewatering, soil surcharging and dust-control measures and provided a construction hotline.
TIDA Infrastructure Manager Wei Zhang presented a comprehensive Stage 2 construction overview on April 16, saying the developer expects to start the main street-improvement work in June 2025, with the work taking approximately 36 months and an estimated total cost of about $135 million to $150 million.
Zhang said Stage 2 covers roughly 36 acres on the eastern side of the island and includes new streets (Trade Winds, Bridal Lane, Marquis Lane, Philip Lane), a neighborhood park (Eastside Commons) and interim stormwater gardens between Building 2 and Building 3. "The developer anticipates to start this Stage 2…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat