Stage 2 construction set to start in June 2025 with multi-year schedule; dewatering and dust mitigation planned

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

TIDA infrastructure manager outlined a June 2025 start for Stage 2 street and utility work on Treasure Island, a roughly 36-acre area with an estimated cost of $135–$150 million and about a 36-month construction window; staff described dewatering, soil surcharging and dust-control measures and provided a construction hotline.

TIDA Infrastructure Manager Wei Zhang presented a comprehensive Stage 2 construction overview on April 16, saying the developer expects to start the main street-improvement work in June 2025, with the work taking approximately 36 months and an estimated total cost of about $135 million to $150 million.

Zhang said Stage 2 covers roughly 36 acres on the eastern side of the island and includes new streets (Trade Winds, Bridal Lane, Marquis Lane, Philip Lane), a neighborhood park (Eastside Commons) and interim stormwater gardens between Building 2 and Building 3. "The developer anticipates to start this Stage 2…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans