Summary

Riley County opened bids on multiple chip‑seal and asphalt overlay contracts at the April 17 meeting and referred the bids to staff for tabulation and recommendation. Bids ranged from roughly $168,500 to $232,475 on chip‑seal and $1.29 million to $1.47 million on overlay alternatives.

Riley County officials opened sealed bids for two roadway procurement packages at the April 17 meeting and directed staff to evaluate the proposals and return with recommendations.

For the chip‑seal package, the county received multiple offers: APAC submitted $168,504.31; Circle C Paving submitted $184,074.66; winners were not yet determined. Vance Brothers provided a bid that included a total of $216,475 with alternate pricing and line items for emulsified asphalt and aggregate. Dennis Asphalt and Bettis Asphalt offered bids in the $180,000 range. Several bids listed start dates in June or August and proposed working‑day periods that ranged from three to 10 days depending on the bidder and option.

For the larger asphalt‑overlay package, Bayer Construction submitted alternate bids of $1,325,705 (alternate 1) and $1,474,140 (alternate 2), and Schilling Construction proposed $1,288,985 (alternate 1) and $1,444,430 (alternate 2); proposed start dates and working days varied by bidder.

After opening the envelopes, the board unanimously moved to send both bid packages to Public Works and procurement staff for analysis and a recommendation to the commission. No contract awards were made at the meeting.

Officials said the chip‑seal start dates were generally targeted for Aug. 1, 2025, while some asphalt overlay work included June start dates; staff will confirm schedules when preparing recommendations. The board is expected to consider award recommendations after staff’s review.

Why it matters: these contracts fund routine county roadwork; the staff analysis will inform which bidders receive awards and how projects will be scheduled this construction season.