Power department updates capacity project progress, generator rebuilds and school outreach

3658782 · April 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported progress on capacity project phases, underground conduit work, generator tune-ups and a student safety demonstration; crews also completed a transformer replacement for a commercial site and continue capacitor bank and substation troubleshooting work.

Power Department staff provided a multi-topic operational update at the March 30, 2025 Hurricane City Power Board meeting, reporting progress on distribution capacity projects, generator maintenance, capacitor bank work and a school demonstration for elementary students.

Construction and capacity: staff said Phase 6 of the city—s Capacity project (on 1300 South from 3 Falls to 920 West) is complete and connected. Phase 4 (underground work through Perkinfield Estates / Scott Stratton—s area) is substantially complete with conduit installed; crews still must pull remaining conductors. Staff said phases 2 and 3 remain to be completed, including work on 2800 West where tangent poles and self-supporting poles are being set in coordination with other utilities and cable contractors.

Transformers and substations: staff reported an upcoming T2 substation upgrade that will replace a 7.5 MW transformer and three regulators with a larger transformer (described in the briefing as larger-capacity equipment) and additional regulators; replacement equipment has been ordered and staff expects work to begin in the coming weeks pending final engineering and vendor acceptance. Staff also described a recent troubleshooting success at Anticline substation where a meter error was traced to a small shorting screw, correcting incorrect phase readings.

Generators and maintenance: staff said crews completed a tune-up and upper-end rebuild work on generator No. 6 and plan a program to perform major maintenance on a generator approximately every year as units reach their 10,000-hour service intervals. Staff reported efforts to install swamp coolers and other cooling measures to improve summer reliability.

Capacitor banks and controls: crews installed a new controller on a capacitor bank near Sky Mountain on 600 North and continue to operate remote controls by radio, with fiber discussed as a potential future control option.

Customer service and community outreach: staff reported energizing the last Terra building in a multi-building development (adding 18 to 20 meters per building) and assisting an interstate customer after a failing center transformer. Staff also described a high-voltage safety demonstration for Hurricane Elementary fourth-grade classes conducted with a high-voltage trailer from Washington City; staff invited council and power board members to attend such demonstrations.

Other items: staff said two department employees will serve as judges at the IPSA Lineman Rodeo May 15; crews also completed numerous service terminations and coordination with development projects.

No formal board action was taken on operational items; staff will continue project work and provide updates at future meetings.