Council discusses stalled sewer work tied to wetlands permitting and Bear River Water coordination
Summary
Council and staff described delays to sewer and subdivision work tied to wetlands jurisdiction questions and the need to coordinate with Bear River Water on metering and billing. The council also discussed easements and trailhead access agreements required for canyon access projects.
Get email alerts on the Utilities And Infrastructure topic
No spam. Unsubscribe anytime.
Willard City Council heard updates about several infrastructure matters affecting proposed subdivisions and canyon access, including a delayed sewer line due to wetlands permitting questions and coordination needs with Bear River Water for water metering and billing.
Council members and staff said construction of a sewer extension for a large proposed development is delayed while jurisdictions and legal counsel consider whether wetlands in the route fall under federal jurisdiction; the council referenced the Sackett court case as a reason the U.S. Army Corps of Engineers and other agencies have not issued a clear ruling. Staff said the uncertainty has stalled obtaining a required 404 permit or equivalent authorization for work across wet areas.
Council also discussed how the city plans to bill for water: staff recommended Willard City read meters and bill customers directly, then remit amounts due to the Bear River Water Conservancy District, because local billing provides the city a mechanism to enforce nonpayment by withholding other municipal services if necessary. Council asked staff to follow up with Bear River Water and report back.
Separately, councilors described near-term work on canyon trail access agreements, noting most draft agreements are complete but that the county must finalize its acceptance of a dedicated trail or right-of-way before the city can finalize easements and perform construction work. Council asked staff and the city engineer to finalize property descriptions and meets-and-bounds to clear remaining title and easement issues.