Council prioritizes street projects and seeks state help for SR-9 congestion
Summary
Councilors outlined a multi-million-dollar street program, including work on 1100 West, 700 West and 100 South, and discussed lobbying state lawmakers and UDOT to address persistent congestion on SR-9; the city is programming engineering and higher levels of street funding over the coming years.
Get email alerts on the Streets And Transportation topic
No spam. Unsubscribe anytime.
Hurricane City councilors used the April 8 budget retreat to review prioritized street projects and to note persistent congestion on State Route 9 that the council said will require state engagement.
Staff presented a list of near-term engineering and construction priorities that includes extension and improvement of 1100 West (work near the airport and southward), rehabilitation of 700 West between SR-9 and 400 South, and renovation of 100 South downtown (a project staff priced at approximately $3.4 million). Councilors said the city is increasing planned street investment and using collected road-related revenues (chip-and-slurry / BNC-style funds) to tackle worst-condition corridors; staff estimated roughly $10 million in near-term street projects queued for engineering and construction.
Several council members raised SR-9 congestion and turning delays at key intersections. One councilor said they will invite state legislators and UDOT representatives to travel peak commute times to observe delays and help prioritize possible lane expansions, left-turn lanes or longer-range interchange solutions. Staff explained some projects are constrained by access and right-of-way, and noted that completing parallel corridors such as 1100 West will make full closures or major reconstructions of 700 West more feasible.
Why it matters: Road condition and traffic flow shape daily commutes, safety and economic activity. The council emphasized that local maintenance and targeted reconstruction complement, but cannot substitute for, state-led improvements to SR-9.
What’s next: Staff will circulate maps of streets slated for chip seal and reconstruction, continue engineering on three projects at a time to keep a steady queue, and coordinate legislative outreach to secure state attention and funding for SR-9 improvements.