Council hears update on sewer permit change and reduced enforcement penalty
Summary
Council member Greg Evans said a stipulation and consent order related to the city’s UPDES permit has been posted for public comment and that the city has applied to change its permit from a discharge permit to a groundwater application, which would reduce some regulatory testing requirements.
Get email alerts on the Environmental Compliance topic
No spam. Unsubscribe anytime.
Council member Greg Evans reported Monday that the city’s sewer‑plant enforcement matter has progressed to a published stipulation and consent order for public comment and that the city has submitted a letter to change its UPDES discharge permit to a groundwater application.
Evans said the consent order appears likely to settle at a lower amount than an earlier estimate: “I think it's, like, 12,000 something versus the 37,000 it was originally,” he told the council. He said the stipulation requires a 30‑day public‑notice period before finalization. The change to a groundwater application reflects that the city is not discharging offsite but rather applying treated effluent to its own property; council members said that change should reduce testing and reporting requirements.
Evans said he will follow up with public‑works staff about outstanding items such as hydrant repairs and a reported water leak. The council did not take formal action on the permit at Monday’s meeting.
Why it matters: A groundwater application rather than an offsite discharge permit can reduce ongoing regulatory burden and sampling requirements, and a smaller consent‑order payment would reduce a near‑term fiscal impact on the city.
What’s next: Staff will monitor the 30‑day public comment period on the consent order, follow up with the state on the groundwater application status and return to council with updates.