Consultant recommends phasing Old Highway work; council hears funding options

3379256 ยท April 1, 2025

Get AI-powered insights, summaries, and transcripts

Sign Up Free
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Jones & DeMille recommended the town phase Old Highway repairs, repaving the roadway first and adding pedestrian/bike paths later as funding permits.

Jones & DeMille, represented to council by Michael Havocin, briefed the Bluff Town Council on April 1, 2025 on a revised approach to the Old Highway (West Seventh) reconstruction. Consultants recommended a streamlined initial project limited to repaving the roadway (stabilize base, 3-inch hot-mix asphalt surface) plus traffic-calming and safety features, with a separate pedestrian/bicycle pathway to be added when funding becomes available.

Why it matters

The Old Highway corridor has been a candidate for comprehensive redesign that included pedestrian and bicycle facilities. Consultants said focusing on repaving first would simplify applications for state-managed funding programs and speed delivery of a usable roadway; a separate pedestrian/bicycle path could be phased in later.

Funding pathways discussed

- UDOT-managed fund or similar program: consultants said the town could pursue a program managed through UDOT that sometimes covers up to 93.3% of eligible project costs (subject to program rules and scoring).

- Community Impact Board (CIB): CIB grants typically combine grant and loan components (consultants noted a representative split might be roughly 50% grant / 50% loan though exact terms vary), which would leave the town responsible for matching amounts and ongoing debt-service obligations.

Council discussion and open questions

Councilmembers asked whether lower-cost surfacing such as chip seal (used elsewhere in the county) had been considered; consultants said the presented plan assumes a hot-mix asphalt surfacing expected to last longer (industry 20-year estimate). Council asked staff and consultants to provide a cost and longevity comparison between chip seal and a 3" asphalt surface and to confirm details such as turn lanes, intersection treatments and how proposed traffic-calming measures would integrate with the town's active-transportation plan.

Next steps

Jones & DeMille will prepare a revised schematic and cost estimate that aligns with funding program parameters to increase the town's likelihood of receiving funds. Council asked consultants to address chip-seal alternatives, phased pedestrian/bicycle options and to return with a proposal suitable for grant submission.