Waller County pays contractors, hears courthouse and justice-center progress update
Summary
Commissioners approved two large contractor payment applications and heard a status report on the new courthouse and justice-center modulars, including a mid–late September interior finish target and a January contract completion for exterior work.
The Waller County Commissioners Court approved two contractor payment applications and received a construction progress report on April 16.
The court approved payment application number 29 to Soudalco in the amount of $5,770,899.53 for ongoing courthouse construction work. The court also approved payment of $924,330.21 (application number 13) to Sidalco for Justice…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat