Board approves $1.7 million modification to airport construction management contract after airport staff cite additional roadway work
Summary
Supervisors approved Modification No. 5 to a construction management professional services agreement, increasing the contract by about $1.7 million to a total not to exceed approximately $16.8 million; airport staff said added roadway stabilization work and other scope changes justify the increase.
Get email alerts on the Airport Construction Contract Modification topic
No spam. Unsubscribe anytime.
The Board of Supervisors approved a resolution authorizing Modification No. 5 to a professional services agreement for construction management services in the amount of approximately $1,700,000, bringing the contract ceiling to about $16,800,000.
Supervisor John Campos questioned the magnitude of the increase — roughly 11 percent on top of the original $15 million contract — and asked staff and airport representatives to explain the reasons. Cathy Weidner, representing the Airport, told the board that the project’s scope expanded from interior Terminal 2 renovations to include roadway work outside the terminal: the road needed stabilization to carry extra project loads, which increased construction management needs. Weidner also said administrative timing and a miscalculation delayed bringing the modification to the board; she apologized for the retroactive submission.
Budget analysts and airport staff stated that the contract was originally competitively bid, that the contractor had relevant experience, and that amending the existing agreement was preferable to re-bidding given the firm's qualifications and continuity needs.
No change to the nature of the work was reported beyond broader construction management tasks tied to the expanded scope; the board adopted the resolution without recorded dissent.
Ending: The board approved the modification so work can continue with the incumbent construction manager; the airport will implement the expanded roadway and terminal work and report per procurement rules.