Court authorizes RFP for K‑Loop bridge rehabilitation after July flood; bid schedule set for November

6490918 · October 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Kerr County authorized advertising an RFP to repair the K‑Loop (Rio Vista) bridge damaged in the July 4 storm, with advertisements planned for Oct. 22 and 29 and a mandatory pre‑bid on Nov. 10.

Kerr County Commissioners on Oct. 14 authorized advertising a request for proposals for the disaster recovery rehabilitation of the K‑Loop (Rio Vista) Bridge, which sustained damage in the July 4 flood.

County Engineer Bobby Gore told the court that plans and specifications have been prepared and reviewed by TEEX Task Force 1, Pate Dawson Engineering, TxDOT, the county engineer’s office and FEMA. The specifications are designed to minimize in‑water work and avoid the need for a temporary bridge, though scheduled short closures are expected during specific operations.

Procurement timeline approved by the court: - Advertisement dates: Oct. 22 and Oct. 29, 2025 - Mandatory pre‑bid conference: Monday, Nov. 10, 2025, at 2 p.m. - Bid submittal deadline: Friday, Nov. 21, 2025, at 2 p.m. - Bid opening and possible award: Monday, Nov. 24, 2025, at 10 a.m.

Gore said the rehabilitation approach reduced the county’s FEMA footprint by roughly $5.5 million compared with earlier scopes and is expected to limit traffic disruption to short, scheduled closures. The court voted unanimously to authorize the RFP.

Why it matters: The K‑Loop bridge is a key local connector; the selected contractor will repair structural damage and reduce the county’s temporary‑bridge cost exposure. The RFP schedule aims to have bidding and award completed by late November so construction can begin once contracts are in place.

Ending: The project will proceed through the public procurement schedule; county staff and engineers will return with contract awards after the bid opening.