District staff told trustees the $5 million maintenance note issued in September 2024 has funded technology infrastructure, new buses and HVAC repairs; FEMA site-inspection reports on hurricane damage were expected in early June.
Get email alerts on the Finance Maintenance Note topic
No spam. Unsubscribe anytime.
District staff updated the Stafford Municipal School District Board of Trustees on the status of a $5 million maintenance note the district issued in September 2024 and on pending FEMA public-assistance claims from last summer’s storm.
Assistant or finance staff reported the board-approved maintenance note has reimbursed prior-year expenditures and funded current-year purchases. The district has spent approximately $2.7 million so far in the current school year and reimbursed about $313,000 of prior-year expenses from the note, the presentation said.
Major expenditures cited included about $1.03 million for network infrastructure with a five-year payment plan (NetSync Network Solutions), roughly $824,000 for five new yellow buses (approximately $148,000 each), and significant spending on HVAC and central plant repairs. Instructional-technology purchases (iPads and AppleCare) totaled about $299,000 across both school years.
Staff also summarized ongoing FEMA public-assistance claims from the hurricane. FEMA approved funding categories B (emergency protective measures), E (buildings and equipment) and G (recreational facilities) and reimburses approved costs at a federal share of 75% for eligible items, staff said. Category B work had been finalized and the district received that reimbursement the week before the meeting, staff said. FEMA completed two site inspections and was preparing site-inspection reports; staff said FEMA estimated the reports would be available in roughly 2–3 months.
Trustees asked clarifying questions about the NetSync contract and whether the network purchase was tied to E-rate reimbursement; staff explained E-rate coverage applies on a campus-by-campus basis and does not always cover central-network infrastructure. Trustees also asked whether FEMA reimbursements would be applied to pay down the maintenance note; staff explained that, when received, FEMA reimbursements are recorded to the district’s general fund and then reconciled.
Board members asked for confirmation that the district had encumbered multi-year payments for the NetSync work; staff said the product was delivered and a five-year payment plan had been put in place, with funds encumbered accordingly. Trustees also asked about damaged gym and library floors at the middle school; staff said those repairs had been estimated and planned for summer work and that some items were included in FEMA damage inventories.
Provenance: The report and trustee questioning are recorded in the meeting transcript during the facilities/finance presentation that followed earlier agenda items.