Commission hears progress updates on new jail, administrative areas and maintenance building
Summary
County staff and contractors reported on construction progress for the new jail, administrative area finish work, parking and a forthcoming maintenance building bid; no new budget appropriation was requested during the report.
Get email alerts on the County Construction topic
No spam. Unsubscribe anytime.
Contractors and county staff updated the Cheatham County Commission on progress at several active county construction sites, including the new jail, administrative interior work, roofing, parking and a separate maintenance building.
A staff member described exterior and interior sequencing: the project team expects to begin putting up security‑type enclosure elements (“the box”) within approximately two weeks and to finish metal roofing in “probably 2 or 3 weeks.” The staff member said the flat roof sections are rubber and the standing seam metal is being installed on the pitched areas. “It’s starting to look like a jail,” a staff member said while reviewing progress with commissioners.
The parking lot work was reported to begin later in the week or in the initial week following the meeting. The staff member said equipment testing has begun inside the building and that personnel are “firing equipment, getting Charles involved” in system checks. The county plans to move certain functions into the new building around November 1, pending completion and plate swap‑over into the old building.
On the maintenance building, county staff said that plans and drawings are complete and the county intends to advertise for bids for about a 14‑day period so that bid results should be available by the next commission meeting. Commissioners asked about the potential consequences of deviating from state procurement and building requirements; legal counsel and other commissioners noted that state fire marshal or state law enforcement could intervene if construction proceeded outside applicable codes or procurement rules.
Commissioners requested tours of the new facility when areas are safe and dried‑in and asked staff to provide internal tours for commissioners before the budget advances too far. No new funding requests or formal votes were recorded during these construction updates.