Board approves $11.18 million GMP for Valley Center High School addition; bond program remains on schedule

2987726 · April 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Guaranteed Maximum Price #4 for Valley Center High School — an $11,180,000 package covering an 18-classroom addition, a CTE storm shelter and kitchen renovations — and was told the bid results were below prior estimates.

The USD 262 Board of Education voted to approve a Guaranteed Maximum Price (GMP) of $11,180,000 for a package of work at Valley Center High School that includes an 18-classroom, two-story addition, a CTE storm shelter addition and kitchen renovations.

Why it matters: The approved GMP advances a significant portion of the district’s bond-funded construction program and authorizes contract execution for the scope described. District representatives said bids returned below both a recent estimate update and the original bond estimate.

What staff reported

Curtis Calvert of Hutton Construction told the board the package attracted roughly 100 subcontractor bids across about 25 trade packages, averaging four to five bids per trade. He said bid results left the project under the district’s previous estimate and under the original bond estimate. The approved GMP covers classroom additions, the CTE storm shelter and kitchen work; staff said one major remaining bid package is the supplemental learning center, which they expect to bid in the next few weeks with a return to the board in mid-May or the next meeting.

Schedule and coordination

Calvert said the construction team is coordinating closely with district staff and plans monthly (and in some cases biweekly) financial reviews to reconcile estimates and commitments. The board was told the elementary addition’s roof and intermediate-school bathroom additions are moving forward, that the elementary building footprint is visible at the site, and that the schedule will be monitored to avoid conflicts among major bid packages.

Board action

The board approved the GMP by voice vote (motion by Sean; second by JR). District staff listed follow-up steps including finalizing contracts under the GMP and continuing to bid the remaining bond-funded components.

Next steps

Staff said they will return with GMP #5 for the supplemental learning center and continue monthly bond financial reviews. The district indicated this GMP is expected to enable continued work on schedule for the bond program.