Scott Park plan advances: engineers outline floodway constraints and timeline for design work
Summary
Crossroads Engineers and the mayor presented a concept plan for Scott Park, emphasizing floodway constraints, ADA access and a target to start construction in late 2026 pending DNR permits and contract approvals.
Get email alerts on the Parks Scott Park Design topic
No spam. Unsubscribe anytime.
Trent Newport of Crossroads Engineers presented preliminary designs for Scott Park to the Franklin City Redevelopment Commission, describing floodway constraints that will shape layout, parking and permitted structures.
Mayor (name not specified in transcript) thanked the commission for acquiring the property and said the city will decide later how to finance the project. Newport said the majority of the site lies within a DNR-designated floodway and the team must avoid "net fill," move dirt on-site and place larger structures outside the mapped floodway. He described preferred features: expanded and additional ball/soccer fields, a clover of four diamonds, a larger diamond, upgraded parking, replacement of a concession building, a splash pad/playground, restrooms and two pedestrian crossings. "The plan... will be all ADA compliant," Newport said.
Newport said Crossroads has subcontractors lined up for geotechnical work, architecture and landscaping, and plans to submit a contract to city staff this week with the intent to appear on the Nov. 18 Board of Works agenda. He noted DNR permits may take up to a year and that his team hopes to break ground in late 2026.
Commissioners and staff asked about restrooms and handicap accessibility; Newport confirmed a restroom/concession/storage building is planned near the large field and that the design will meet ADA standards though some slopes may approach maximum allowable grades. Newport said the team has begun conversations with the county and expects to coordinate closely on permitting.
No formal RDC vote was recorded on the engineering contract at this meeting; staff said they will prepare contract documents and, if budgets and advertisement deadlines allow, return with a resolution for approval at the November meeting.