Wenatchee approves $144,814 change order to rewire South End Bike and Access Bridge

6490344 · October 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City Council authorized construction change order No. 6, $144,814, to convert the South End Bridge lighting from a three‑phase 480‑volt system to a single‑phase 240‑volt system, a change staff said improves maintenance access and safety and falls within project contingency.

The Wenatchee City Council authorized a $144,814 construction change order Tuesday for the South End Bike and Access Bridge to adjust the bridge’s electrical and lighting configuration.

Ryan (Carmel Engineering Services), who presented the change, said the project team shifted from a three‑phase, 480‑volt design to a single‑phase, 240‑volt system to improve maintenance safety and efficiency. He said the rewiring allows maintenance staff easier access to junction boxes and reduces the need for workers to hang over the side of the bridge to service lighting.

Ryan described the change as an opportunity to right‑size the electrical configuration, accommodate the bridge’s rail geometry and replace an initial rope‑lighting concept with fixtures that are easier to maintain. The council was told the work also allowed the project team to relocate junction boxes and take advantage of existing vaults.

Why it matters: City staff said the change avoids ongoing maintenance hazards, fits within the project contingency and will reduce the long‑term operational burden on the city’s crews. The change order was described as within the project’s estimated budget.

Motion and outcome: Council Member Pfeiffer moved and Council Member Atkinson seconded authorization for the mayor to approve Construction Change Order No. 6 for City Project No. 2201.2. The motion passed by voice vote.

Ending: Project staff said several smaller change orders are still being finalized; the council approved the change order No. 6 so work can proceed. The item is subject to Washington State Department of Transportation concurrence as noted in the motion.