District recommends contract to replace Stephenson pool filtration system; sinking fund to pay $466,200 estimate

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff recommended awarding a public bid to Barzini Contracting to replace the Stephenson High School pool filtration system at an estimated total of $466,200 (hard construction $423,781 plus $42,419 contingency); work would use sinking fund dollars and begin late May/early June with a 4-6 week schedule.

District staff told the building and site committee they plan to replace the end-of-life pool filtration system at Stephenson High School and recommended awarding the work to Barzini Contracting as the lowest responsible bidder; the committee heard the recommendation and staff said the item will proceed to the regular meeting for contract approval.

Colin (facilities) explained the existing filtration system was first installed in 2010 and is at end of life; replacement parts are becoming unavailable and maintenance staff warned the next failure could leave the pool out of service for a prolonged period. The work scope includes replacement of the filtration system, lighting upgrades in the filter room and grout repairs while the pool is drained.

The project was publicly bid; staff said three bidders consulted the project but only one bid was received because schedule and summer manpower conflicts prevented two contractors from submitting proposals. After a post-bid interview, staff recommended Barzini Contracting as the lowest responsible bidder. The recommendation presented a total amount of $466,200: a hard construction amount of $423,781 and a construction contingency of $42,419. Staff said the work would be performed under a standard AIA contract pending legal review and funded from the sinking fund.

Staff said work is planned to start in late May or early June with a 4-6 week construction window; similar work at Churchill and Franklin pools is planned for next year. No formal contract award occurred at the study session; staff will request formal board approval on the regular meeting agenda.

Clarifying details: one public bid received; recommended contract value $466,200 total, funded by the district sinking fund; last major work on the system was in February 2010 (life expectancy ~15 years).