Sports authority approves escrow accounts and environmental change order, receives stadium progress and DBE/local participation update
Summary
The Sports Authority authorized establishing Truist Bank escrow accounts for contractor retainage and approved an $83,810 change order for environmental QA services for the South Broad District Ballpark.
The Sports Authority of the County of Hamilton and the City of Chattanooga on April 2 authorized the chair to execute documents to establish escrow accounts with Truist Bank for retainage related to the construction manager-at-risk contract for the South Broad District Ballpark and approved change order No. 1 for SNME Inc. to provide additional environmental quality-assurance services during construction, increasing that task order by $83,810 to a total $156,420.
The board also accepted a financial progress report that added a new line item, "West 20 Sixth Street," to account for stadium-adjacent infrastructure. Authority staff said the city allocated $5,700,000 to the authority for the current fiscal year for that infrastructure and an additional $4,300,000 is planned for the next fiscal year, for a combined total budget of $10,000,000.…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat