MAPS sidewalks and bike-lanes projects: board approves multiple change orders, hears progress reports and signs off to advertise Phase 2A
Summary
Board heard construction updates for sidewalks and bike-lane projects, approved several change orders and amendments (totaling multiple hundred thousand dollars) and recommended final plans for Phase 2A be advertised for bids.
Engineers and contractors gave progress updates on multiple MAPS sidewalks and bike-lane projects and the board approved several routine change orders, amendments and a set of final plans to be advertised for bids.
Mark Long of Smith Roberts Baldeschweiler updated the board on sidewalks Phase 1A, describing three general alignment areas (Quail Creek, Britton Road and Northwest 23rd at Classen) totaling roughly 27,000 linear feet of improvements. He said Nash Construction holds the contract at $3,255,795, with work starting in July of the prior year and anticipated completion in June. Long described added alignments (including Walker Avenue and Park Place) that prompted…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat