Sutter Butte board awards Tudor flood-risk construction contract to Nordic Industries

2963131 ยท April 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Sutter Butte Flood Control Agency Board of Directors unanimously approved awarding the Tudor Flood Risk reduction construction contract to Nordic Industries after the low bid of $8,894,230 came in well under the agency's engineer's estimate.

The Sutter Butte Flood Control Agency Board of Directors unanimously approved awarding the Tudor Flood Risk Reduction Project construction contract to Nordic Industries after staff said Nordic submitted the low qualified bid.

The board approved plans, specifications and the contract award at its April 9 meeting. Michael Bessette, the agency's executive director, told the board that bids opened the previous Thursday and that "our low bidder, our qualified contractor low bidder was Nordic Industries." He said the bid came in at $8,894,230, "and essentially it's $7,000,000 below our engineer's estimate."

Bessette said the agency has discussed the project and schedule with Nordic's president and is ready to move forward if the board approved the award. "If the board approves the contract today, I'll move forward and work with Nordic Industries, get bonds and insurance, get the contract signed, issue a notice to proceed, and we'll get rolling on this project," he said.

Why it matters: the Tudor project is a locally led levee/river work intended to reduce flood risk in the Feather River corridor. The low bid lowers the agency's anticipated construction cost compared with its engineering estimate and reduces the amount the agency would need to cover from other funding sources.

Key details and next steps - Bids: Bessette said the agency received three bids; all came in below the engineer's estimate. Other bidders were reported as higher (transcript names given). Nordic's bid was $8,894,230. The engineer's estimate was discussed as roughly $16 million during the meeting. - Permits and federal review: Bessette told the board the Army Corps of Engineers Section 408 review packet had left the district for the San Francisco office and the Corps requested a 14-day turnaround. He said the Corps' schedule was consistent with receiving 408 approval "at the end of this month and getting a letter of permission issued first week in May." The Central Valley Flood Protection Board was also expected to issue an encroachment permit at its April meeting, and staff said final permits should be in hand before work begins. - Schedule: Staff said they expect to wrap up permits and start construction in May if all approvals arrive on schedule. The agency also said it plans a groundbreaking ceremony in the week of May 26 and invited federal and state officials to attend.

Board action The board voted to approve the plans, specifications and award of the Tudor Flood Risk Reduction Project construction contract to Nordic Industries. A roll-call vote was taken and the motion passed unanimously.

What the board and staff said - Michael Bessette, executive director: "The bid was for $8,894,230 and essentially it's $7,000,000 below our engineer's estimate." He said Nordic is "excited to get the project and move forward." He also described the status of the Corps' 408 review and the expected schedule for a letter of permission.

Looking ahead Staff said they will finalize bonds and insurance, sign the contract, issue a notice to proceed and coordinate the planned May groundbreaking. The board asked several clarifying questions about bids and schedule during the meeting.

Votes at a glance - Award Tudor Flood Risk Reduction Project construction contract to Nordic Industries: approved unanimously (roll-call vote).