Union County Water unveils new online guide for builders; staff says full process can take about eight months
Summary
Union County Water launched a standalone website with a detailed 10‑step new‑development process, checklists and links to permitting portals; staff told commissioners the fastest end‑to‑end approval timeline is about eight months, with larger projects taking 12–18 months.
Get email alerts on the Development Permitting Website topic
No spam. Unsubscribe anytime.
Union County Water staff demonstrated a newly launched website aimed at developers and builders and outlined the county’s new‑development process, timelines and resources.
Crystal Panico, the county’s new development program manager, explained the website (unioncountywater.org) centralizes guidance, forms, checklists and links to the county’s Evolve portal. The site lays out a 10‑step review process derived from the county’s water and sewer extension ordinance and includes sketch plan and construction plan checklists, links to technical specifications and a description of the capacity allocation step.
Panico told commissioners her team averages 120–130 plan reviews per month. She said the fastest the full process can be completed, from sketch plan through permitting and development agreement, is about eight months if submittals are complete and timely; larger developments often take 12–18 months. Staff emphasized the website does not provide “will‑serve” letters or an up‑front capacity allocation — those commitments come later in the review process.
County communications said the page has tracked roughly 1,000 views since October; staff and commissioners encouraged making the link easy to find (email signatures, redirect from the county website) and using the site to answer frequent developer questions about capacity and next steps.