Intermediate school design 75% complete; construction manager running pricing rounds

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project manager and construction manager told the board design is roughly 75% finished, three rounds of contractor pricing are planned and the team is preparing submittals to review agencies; the project is slightly behind schedule but recoverable.

District project staff and the construction manager updated the board on the intermediate school project, reporting the design is roughly 75% complete, and that three rounds of construction pricing are underway to refine the guaranteed maximum price (GMP).

Project manager Mike Spade introduced Christian Salazar of CR Crawford Construction, who said the team…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans