Cotati awards 2025 street-improvement contract to American Asphalt; orders prevailing-wage spot checks

2905126 · April 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Cotati City Council voted 5-0 to award the 2025 Street Improvement Project to American Asphalt Repair & Resurfacing Company and to authorize execution of related construction and construction-management contracts.

The Cotati City Council voted 5-0 to award the 2025 Street Improvement Project to American Asphalt Repair & Resurfacing Company and to authorize the city manager to execute the construction contract and a construction-management and inspection-services agreement with Green Valley Consulting Engineering.

Public Works Director and city engineer Craig Scott presented the project background. Bids opened March 18 and five bids were received; the low bid was about 12.5% below the engineer’s estimate. Scott said the low bidder had completed the city’s 2024 pavement-preservation work without substantive contract-performance issues and that the city would hold a one-year warranty bond after final acceptance.

Several public commenters raised prevailing-wage and enforcement concerns after the city received a letter from the Foundation for Fair Contracting that flagged alleged prevailing-wage complaints involving the apparent low bidder. Council Member Sparks said she pulled the item from the consent calendar to request stronger payroll oversight and asked staff to add prevailing-wage spot checks to Green Valley’s construction-management scope. Sparks said the city’s standard certified-payroll submittals are required but that spot checks or worker interviews are a common additional safeguard on projects that receive federal funds.

Director Scott said the city collects certified payroll reports for public-works projects at regular intervals and posts them as public records; he confirmed that the city has performed spot checks on projects funded with federal dollars. Given the low bid and the bid-package responsiveness, staff recommended awarding the contract while adding the prevailing-wage spot-check direction for construction management.

Council approved the award and the professional agreement and directed staff to request the prevailing-wage spot-checks from Green Valley Consulting Engineering; council also authorized change orders or amendments to professional agreements within the project authorization amount. Council members noted that the project budget includes a thin contingency (staff estimated roughly 0.7% remaining in contingency, about $7,000) and that cost increases would require scaling scope or returning to council if beyond staff authorization.

The contracts will be executed and construction scheduled per the city’s normal public-works procurement procedures. Staff will post bid tabulation results and contract documents on the city website.