Council authorizes emergency sewer main repair south of Judson Road for $133,288.59

2904587 · April 8, 2025

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Live Oak approved a contractor proposal to replace a failing 700-foot sewer main (pipe-bursting) south of Judson Road, accepting a Fuquay Incorporated proposal for $133,288.59 plus a 10% contingency; the work is emergency repair on an easement and will proceed upon contractor notice.

The Live Oak City Council on April 22 approved a resolution accepting a proposal from Fuquay Incorporated (also referenced as Fuquay, LLC/Inc.) to repair a failing sewer main located south of Judson Road, near the intersection with Gunn Road. Council approved the proposal amount of $133,288.59 and authorized a 10% contingency for a total authorization of $146,617.44.

Public works staff said approximately 700 feet of sewer main in an easement (outside the roadway) is failing and cannot be repaired in place, so an in-place replacement using a pipe-bursting method is recommended. "They run something through there. They break the old pipe. They pull a new one right in its place, so we don't have to dig it all up," said Mr. McNew (staff member).

Because staff classified the situation as an emergency, they used a purchasing cooperative to obtain a preapproved contractor rather than sending the work to a standard bid process. Fuquay Incorporated provided the proposal to perform the pipe bursting. Staff told council the contractor has not started work and is awaiting authorization; bypass pumping is in place to keep the system functioning until replacement begins.

Council members asked about the location and previous sewer camera surveys. Staff said the line is within a private property easement (the Alpha line from Fiddler's Green) across from Gunn Road and that the line had been identified as an issue in ongoing sewer inspections; some CCTV/inspection work remains to be completed on other lines.

A motion to accept the proposal and authorize a 10% contingency passed unanimously, 5-0. Staff said crews expect to mobilize as soon as the contractor confirms availability.

Votes at a glance: Proposal from Fuquay Incorporated to repair sewer main south of Judson Road — approved 5-0.