Council hears progress report on street‑patching contracts; staff proposes additional $2 million contract for large repairs
Summary
City staff reported that Advanced Pavement Maintenance is nearly finished with a $2.5M contract and LA Fuller & Sons is roughly half finished with its $2.5M contract; staff outlined costs and recommended exhausting the contracts and returning with a full program evaluation.
City staff reported on the status of two patching contracts that began in late 2024 and are being used to accelerate pavement repairs after a harsh winter.
Public Works Director Alan Harder said two contractors were awarded $2.5 million contracts each in October 2024: Advanced Pavement Maintenance and LA Fuller & Sons. Advanced Pavement Maintenance has invoiced about $2,480,000 (≈99.4% complete). LA Fuller has invoiced about $1,300,000 and is roughly 53…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat