Council approves library 'privacy pods' installation; members debate contingency funds
Summary
San Leandro city council approved $269,806 for prefabricated privacy pods at the Main Library, including a 9% contingency to cover structural engineering work and potential tariffs; council debated whether contingencies should return for explicit approval.
Get email alerts on the Libraries topic
No spam. Unsubscribe anytime.
The San Leandro City Council on April 7 approved a contract to install prefabricated "privacy pods" in the Main Library, voting 7‑0 after discussion about a contingency line item.
Library Director Brian Simons told the council the pods are prefabricated and require floor anchoring; because the library building is about 25 years old the project includes a structural engineering review. Staff said the contingency – about $24,250 (roughly 9% of the contract) – is intended to cover possible alternate anchoring approaches discovered by the structural engineer and the risk of tariffs on imported components.
Council members questioned the contingency and asked for assurances about cost control. Simons said staff had identified budget offsets elsewhere and would seek multiple engineering options before spending contingency funds. The director also described how the pods will be managed: the city will use a reservation process similar to the Manor Branch study rooms, with two‑hour blocks available up to 24 hours in advance, and library staff will monitor usage rather than automating reservations.
Details provided in the meeting: six pods will be installed — four 4‑person pods and two single‑person pods, allowing up to 18 users simultaneously if fully occupied. Electrical hookups are required but the electrical work is contracted and billed separately from the pods contract; staff said electrical exists in the building and electricians will connect the units. Lead time for the prefabricated pods is approximately nine weeks after contract signing.
Councilmember Aguilar moved to approve the contract with contingency included; Councilmember Gonzales later withdrew an earlier motion to strike the contingency and ultimately the item passed on a motion by Gonzales and second by Aguilar, 7‑0. Councilmember Simon described a 9% contingency as "relatively reasonable" for construction projects but several council members urged staff to tighten contingency oversight in future procurements.
Next steps: staff will proceed with contract execution, schedule structural engineering scans, and coordinate electrical work with Public Works and city electricians.