County approves replacement of Tarboro convenience-site building; cost estimates vary, ADA work required

2892790 · April 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Edgecombe County approved a special-use permit allowing the county to replace a wooden convenience-site building in Tarboro with a concrete structure of about 300 square feet. County staff said the project is budgeted but contractor estimates varied widely; the building must be accessible and will require bids and permitting.

The Edgecombe County Board of Commissioners on April 7 approved a special-use permit allowing the county to replace and slightly expand a convenience-site building at 1429 Arches Chapel Road in Tarboro.

Planning staff described the existing structure as a roughly 200'square-foot wooden building used by site employees. Assistant County Manager Michael Matthews said the timber structure has experienced water intrusion and is effectively beyond repair; the county proposes to replace it with a concrete block building of roughly 300 square feet.

Estimates discussed at the meeting varied. Matthews said one architect returned a design estimate of about $200,000; a local contractor told staff he expected a cost in the $35,000'$50,000 range; the county maintenance director estimated $60,000'$70,000. County staff reported $80,000 budgeted in solid-waste capital for the project.

Matthews told commissioners that the new building will require handicap-accessible parking and an accessible route; the existing structure lacks those features. He said the county will bid the work and cannot perform the full construction in-house.

The board approved the special-use permit by motion and voice vote. Staff said the project will undergo site-plan review and require development permits before work can proceed. Matthews said the county's long-term plan is to replace similar convenience-site buildings on a staggered schedule so facilities match and are durable over time.