County engineer says Justice Center is about 27% complete; MEP work to drive schedule

2891476 · April 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County engineer John Hernandez told the San Patricio County Commissioners Court that the Justice Center project is roughly 27% complete, with mechanical, electrical and plumbing work set to drive the schedule toward a spring 2026 finish.

John Hernandez, the county engineer, told the San Patricio County Commissioners Court that construction of the county Justice Center is about 27% complete and that upcoming mechanical, electrical and plumbing work will control the project schedule.

Hernandez said this month’s payout on the project was approximately $3.2 million and that work completed to date includes second-floor concrete on metal deck, third-floor steel and wire mesh installation, and delivery of metal stud framing and an emergency electrical generator. “The…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans