District updates on softball/baseball fields and approves May Roberts kitchen contract
Summary
Facilities manager updated the board on construction of softball and baseball fields, concessions and the concessions building; the board also approved a $382,060 general-contract bid to Alpine Construction Management for the May Roberts kitchen remodel with a recommended 10% contingency and named subcontractors.
Facilities manager Bob Bennett told the board the district has been leading construction on two North fields (JV/practice) and working with community volunteers and the Friends of Softball group on fundraising and finishing work.
Bennett reported completed items on the softball field: concrete work under fencing and backstops, dugout pads, removal of foul sod and installation of foul-line fencing. He said two backstop components remained to be fully installed and estimated…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat