Planning Commission report: construction-trailer locations for Black Desert Resort amended and approved
Summary
The Ivins Planning Commission approved a Class 4 conditional‑use permit amendment allowing three modular construction trailers at relocated sites within the Black Desert Resort construction footprint; the Planning Commission found the trailers screened and relocated away from the parkway.
Get email alerts on the Planning topic
No spam. Unsubscribe anytime.
Pam, representing the Planning Commission, reported to council that the commission met March 18 to consider a Class 4 conditional‑use permit amendment for the temporary placement of three construction trailers associated with the Black Desert Resort construction.
Pam said the petitioner has relocated the three modular buildings to reduce visibility from Snow Canyon Parkway: one trailer moved south where a future parking lot and water park are to be built and is no longer visible from the parkway; a second trailer sits across from the hotel and is not visible from the parkway; the third trailer was moved to Lot 17 in the North Village and will be mostly screened by a planned lava wall once construction completes.
During the public hearing, nearby resident Jerry Armstrong thanked the city for protecting vistas and urged proactive adherence to the general plan's view-protection goals. The Planning Commission discussed other visible construction equipment such as pods and said the petitioner had committed to moving them to minimize viewshed impacts.
Pam reported the Planning Commission approved the amendment, finding that the applications satisfied access to utilities, relocation and screening requirements, and that the amended locations addressed prior concerns.
Why it matters: The decision allows Black Desert Resort to continue on‑site construction operations with temporary modular buildings in less‑visible locations, a change that planning staff and the commission judged compatible with general‑plan view protection goals.
Ending: Council received the Planning Commission report and no council action was required; staff will monitor implementation and the completion of screening features such as the lava wall behind Lot 17.