Commissioners approve one change order for new recycle center, table a second pending contractor accountability review
Summary
The board approved change order CO-009 to extend fire-suppression work for the recycle center and tabled CO-008 while seeking contractor accountability and design clarifications for additional front-awning lighting and a covered outdoor storage ceiling.
Get email alerts on the Capital Projects Change Orders topic
No spam. Unsubscribe anytime.
White County commissioners voted to accept change order CO-009 for the new county recycle center and to table CO-008 pending further discussions with the general contractor and the design firm.
Staff explained that the project has encountered design omissions. One change order involves lighting that was ordered but does not fit the awning that was purchased; after redesign the intended solution is to mount lights to the building wall instead of in the awning. The other change order (CO-009) pertains to adding a ceiling in an outdoor storage area and extending the fire-suppression drop through that ceiling; the construction manager offered to provide labor for ceiling installation and the change-order cost—about $2,400—covers the fire-suppression extension.
Commissioner comments said the county expects contractors and the design firm (Garmon/Kettle Hut and the design consultant named in discussion) to accept more accountability when design omissions force change orders. The board approved CO-009 (voice vote) and moved to table CO-008 so staff can continue negotiations before bringing the matter back at the next meeting.
Ending: Staff will continue discussions with the contractor and design firm and return with proposals and cost-sharing options on CO-008 at the next meeting.