Citizen Portal

Get email alerts on the Land Use Planning topic

No spam. Unsubscribe anytime.

White County adopts 12-month moratorium on large-scale solar, wind and storage projects

Commissioners' Meeting - 03-17-2025 · March 17, 2025

Summary

The White County commissioners voted to place a 12-month development moratorium on commercial and large-scale solar, wind and energy storage projects to allow time to update local planning and land‑use rules.

White County commissioners on March 18 voted to establish a 12-month moratorium on commercial and large-scale solar, wind and energy storage projects within the county.

The moratorium was presented as an ordinance “establishing development moratorium on commercial or large scale, solar and wind, alternative energy generation and storage systems or facilities.” Commissioners said the pause will give staff and elected officials time to complete comprehensive‑planning work and write ordinance language before new projects move forward.

Supporters of the moratorium said it will allow the county to “get the comprehensive planning pieces in place” and to add or subtract provisions after review. The ordinance was read by title during the meeting and received no late amendments. After brief public comments and a motion, the board approved the 12‑month moratorium with a voice vote.

The motion passed with commissioners voting in favor after the reading by title. Commissioners clarified the moratorium applies inside county limits and does not automatically bind municipalities or town boards; it covers county development approvals until the county adopts new rules.

County staff said the moratorium is intended to be temporary, giving planners and the board time to prepare regulations and standards that would guide future large‑scale renewable projects. The vote does not cancel or change already approved permits; it stops new county applications subject to the ordinance from being accepted or processed during the moratorium period.

Next steps identified by commissioners include drafting ordinance language, coordinating with planning staff on updates to the comprehensive plan and scheduling follow‑up meetings over the coming months to craft the regulatory amendments.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source