Council approves Germania Park Phase 5 capital improvement project with condition to allow street removal if vacation proceeds
Summary
After a continued public hearing, the council voted unanimously to proceed with capital improvement project 1114 (Germania Park Phase 5), with contract language allowing the city to remove a portion of Linn Street before July 1 if a separate street vacation application is approved.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
The Mankato City Council voted unanimously March 10 to advance Capital Improvement Project 1114, Germania Park Phase 5, following a continued improvement hearing that began in January. Council action included closing the public hearing and authorizing staff to proceed with design and bidding; the approved motion included contract language allowing the city to remove a portion of Linn Street prior to July 1, 2025, if a pending street vacation is later approved.
City Manager Arndt told the council the hearing had been continued from Jan. 13 to resolve issues raised by an adjacent developer and by Grace Baptist Church, which has filed a separate Linn Street vacation application for a 66-foot-wide segment between Sixth and Seventh avenues. Arndt said staff believe they have addressed the developer’s concerns about the Eighth Street portion and that the project can proceed.
The council heard from Brett Skillbred, who identified himself as representing both Pentagon Acquisition (developer for Eighth Street) and Grace Baptist Church’s vacation application. Skillbred said both parties support moving the project forward and are comfortable with contract language that would allow the city to remove the Linn Street segment if the vacation application receives the city’s approvals.
Arndt described two paths for the council: proceed with the project with contract language to accommodate a later vacation decision, or delay the Germania Park project. He recommended proceeding because of time-sensitive design and bidding considerations for the 2025 construction season.
The feasibility study included an estimated total project cost of $2,132,975.78 and an estimated $705,582.52 in special assessments (about 33.08% of the total), which Arndt said meets the 20% threshold under Minnesota Statutes Chapter 429 for special assessments. Arndt also told the council that the city will perform a special-benefit appraisal before the special-assessment hearing under the city’s policy.
After a motion to move forward with the project and to close the hearing — moved and seconded by council members as recorded in the minutes — the clerk recorded a unanimous roll call of approval. The motion included direction to proceed with the project as proposed and to add contract language allowing removal of the Linn Street portion if the vacation is approved, with a July 1, 2025, cut-off for that conditional removal.
The action advances design and bidding steps for Germania Park Phase 5; the city clerk and staff will schedule subsequent special-assessment and final-adoption hearings as required by the city’s standard capital-improvement process.