Hillcrest elementary nears completion; district schedules July turnover, emphasizes safety features
Summary
Ken Crawford, the district’s executive director over support services and athletics, told the Ogden City School District board its new Hillcrest elementary is largely dried in, has permanent power connected, and is on schedule for turnover by July 1, with safety‑focused design features including masonry shelter spaces between classroom pairs.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
Ken Crawford, the district’s executive director over support services and athletics, told the Ogden City School District Board at the March work session that construction of the new Hillcrest elementary is largely on schedule and that the district expects building turnover by July 1.
“The building is dried in,” Crawford said, noting carpet and millwork installations, large areas of installed exterior glass, asphalt paving to limit mud tracking and the recent connection of permanent power. He said many interior finishes — painting, carpeting and millwork — are already complete in several wings and that furniture procurement is being finalized with delivery planned for shortly after turnover.
Crawford walked board members through design and safety details, including a central courtyard with seating and a platform that can double as a presentation area, STEAM/teams labs overlooking the courtyard, and a larger vestibule at the main entrance designed as a controlled parent waiting area.
Safety features and classroom layout
Crawford described an intentional safety design incorporated into classroom clusters: between each pair of classrooms there is a fully grouted masonry room with storage that can be accessed from either classroom and used as a protective shelter if needed. “It’s a fully grouted masonry bunker, basically, between 2 classrooms that have shelves on it…should be a very safe place to be,” he said.
The building is arranged in four wings with grade clusters and teacher collaboration spaces. Crawford said classroom zones include shared bathrooms, single‑use restrooms, drinking fountains and sinks for hands‑on work. Collaboration spaces include nine workstations so that instructional support staff, ESPs and other district staff have a place to work inside each wing.
Branding, accessibility and schedule
Crawford said the board previously chose to retain the Hillcrest name and that the design team has incorporated a crest and thematic branding for the four wings (Terra, Aqua, Ignis and Ventus). He noted some design choices — masonry rather than the originally proposed metal paneling — produced both aesthetic and cost benefits.
He reiterated the schedule: the district expects turnover by July 1 so staff can move in, furniture can be installed and teachers and support staff can complete preparations ahead of the fall term. “The building should be turned over to us by July 1,” he said.
Questions and follow‑ups
Board members asked about furniture specifications, shelving depth in the media center and plans for an open house or ribbon cutting; Crawford said the district typically plans an unveiling around August or coordinates with back‑to‑school events but may hold a separate early event. He also said the district is finalizing glazing safety film specifications in response to House Bill 84 and related guidance, and that film installation is pending final specification.
Crawford closed by noting that some exterior landscaping and equipment installation remain and that final inspections and commissioning will precede turnover.
Provenance: Crawford’s construction update and subsequent Q&A appear in the transcript and include the progress and safety details summarized here.