Council approves park grant application and awards Hoeghman Park construction contracts
Summary
Lock Haven voted to apply for a $150,000 DCNR grant (matched by $150,000 local funds) to renovate Santa Park and approved rebid construction contracts for Hoeghman Park Phase 1 and Phase 2, subject to DCNR approval.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
The Lock Haven City Council on March 17 authorized application for a Pennsylvania Department of Conservation and Natural Resources (DCNR) grant of $150,000 to support renovations at Santa Park and approved related local matching funds if the grant is awarded.
City staff said the $300,000 project (including the $150,000 local match) would fund restroom renovation, new tennis courts, a basketball court and a walking path. Staff described the work as phase 1 of multiple planned phases and said future elements could include a splash pad, exercise path and pavilion subject to later funding.
Council also opened bids and approved low bids for Hoeghman Park Phase 1 and Phase 2 rebids. The low combined bids for Phase 1 totaled $955,867.45 (general construction low bid $838,566.65 from Roman Excavation; HVAC $2,301.80; plumbing low $46,174; electrical low $68,825). Council approved award of Phase 1 bids contingent on DCNR and grant approvals. Council separately approved Phase 2 low bid of $526,477.95 to Bowman Excavation; that award is also contingent on grant approvals.
Staff said the rebid produced more competitive pricing and estimated savings of approximately $200,000 compared with the original bid. Council members asked about construction timeline; staff said work should be completed by August for Phase 1 and that a ribbon‑cutting would follow.
Votes to approve the grant application and to award the rebid contracts were recorded in the meeting minutes; staff emphasized coordination with DCNR and continued engineering estimates for phase sequencing.