Commission hears update on Project Restore 2.0; building rehabs on West Main advance slowly
Summary
Staff updated the commission on state‑funded Project Restore 2.0, including exterior work underway at 71 and 273 W. Main and proposed activity at 66–68 W. Main; staff said work is progressing, interior rehab remains next, and funding/timing coordination with grants and procurement continues.
Get email alerts on the Downtown Rehabilitation topic
No spam. Unsubscribe anytime.
City staff reported progress on Project Restore 2.0 and other downtown rehabilitation efforts, saying exterior repairs are underway at a pair of vacant buildings on West Main and that applicants are preparing interior work and funding requests.
Staff said the property owner for 71 and 273 W. Main (near Rock Salt) has completed exterior improvements and an addition; interior work remains. Contractors and the applicant have begun progress meetings and staff is coordinating grant funding timing so reimbursement or matching funds can be made available within the grant schedule. Staff said the project team targets mid‑year progress and aims to complete projects by the end of the calendar year if funding and permitting allow.
Staff also reported interest in 66–68 W. Main, across the street, where the owner has indicated plans for two new businesses and two upstairs apartments; that property had not submitted a city funding application tied to the Project Restore grants at the time of the meeting. Staff said some owners have pursued private restoration funds and that the city’s facade/infrastructure grants have been quickly allocated and are beginning to be spent.
Commissioners asked about timing, scope and whether the same owner’s multiple properties complicate delivery; staff said the size of the portfolio and the number of parcels can lengthen timelines and that the city is balancing grant disbursement and permitting to keep projects moving.
Ending: Staff will continue progress meetings and coordinate grant disbursements and permitting; the commission asked staff to keep the board informed of milestone changes.