At a glance: Torrington Inland Wetlands Commission actions, April 1, 2025
Summary
Summary of permit decisions and administrative acceptances taken during the Torrington Inland Wetlands Commission meeting on April 1, 2025.
Get email alerts on the Meeting Roundup topic
No spam. Unsubscribe anytime.
The Torrington Inland Wetlands Commission on April 1 took the following actions during its regular meeting at Torrington City Hall: Michael Benvenuto 1739 Weed Road; Theresa Guzman Sanchez 1477 Toringford Street; John Miller 2480 Newfield Road. The commission also accepted the City of Torrington's Red Mountain Trail application (see separate article) and handled enforcement at 516 Mountain Road (see separate article).
Michael Benvenuto, 1739 Weed Road (Assessor Map 202, Lot 003, Block 012) - Action: Wetlands crossing permit for a new single-family home in the Upland Review Area. - Conditions: Standard conditions plus (1) surveyed wetland boundaries to be posted with metal markers with design and spacing to be approved by the city wetlands enforcement officer; and (2) plant species for the required rain garden to be approved by the city wetlands enforcement officer prior to installation. - Outcome: Permit granted (motion carried).
Theresa (Teresa) Guzman Sanchez, 1477 Toringford Street (Assessor Map 246, Lot 002, Block 058) - Action: Wetlands restoration permit (application arose from a notice of violation for clearing/mowing into mapped wetlands). - Staff recommendation: Allow natural revegetation, post wetlands markers; reserve agent discretion to require restoration of any disturbed area if necessary. - Outcome: Application accepted as not a significant activity; motion carried.
John Miller, 2480 Newfield Road (Assessor Map 230, Lot 001, Block 001) - Action: Application for septic construction and stormwater diversion that may affect wetlands. - Staff notes: Applicant must revise plans to show accurate storm piping (15-inch piping) and clarify where the outfall will be relative to existing wetlands and the Naugatuck River; Torrington Area Health and the city engineer will require modifications during review. - Commission action: Application accepted for processing; determination of significance deferred until final plans submitted. Motion carried.
Votes and procedure - Each of the above items was moved and seconded on the record and the chair announced "Motion carries" after voice votes of "Aye." The transcript records voice votes but does not include roll-call tallies. Where conditions were set, staff was instructed to verify compliance as plans are finalized.
Administrative notes - Minutes for the March 4, 2025 meeting were approved by voice vote at the start of the meeting. - Staff will process zoning permits and other administrative steps as required after wetlands approvals are finalized.
This summary lists the formal actions recorded in the commission minutes for April 1, 2025. For discussion detail, conditions, and enforcement actions, see individual transcripts and the two separate articles on the Red Mountain Trail and the 516 Mountain Road enforcement action.