Summary

City officials reported engineers found clay throughout a test trench in the Stuart pond, plan to partially refill and monitor seepage while pursuing sewer‑system work; sewer project bids are expected next week.

City staff told the Spring City Council that recent field tests of the Stuart pond showed extensive clay beneath the surface and that the city will refill the pond by about 1 foot and watch the level before deciding next steps.

"Plenty of clay — it was all 3 feet deep was clay," said Council member Randy Strait during the department reports, describing results after a trench was dug across the pond. City staff said the trench measured roughly 3 feet deep by about 50 yards long and about 2 feet wide; engineers will run a leach test once the water is in place.

City staff and the consulting engineer said the trenching and subsequent tests reduced the scope and estimated cost of earlier remediation options. Council members said the city had received written confirmation from an engineer that interim overflow protection would be adequate during monitoring.

Separately, council members said they expect bids for an upcoming sewer project to arrive next week. No contract award was made at the meeting; staff said bid review and recommended action will come back to the council for a formal vote.

The city will monitor the pond over several weeks after the fill and perform the engineer‑requested leach tests before committing to construction or larger remediation contracts.