Syracuse-Wawasee Trails gives progress report on Wawasee South segment; board acknowledges prior support letter
Summary
The Syracuse-Wawasee Trails executive director updated the parks board on the Wawasee South 2.2-mile trail segment engineering and fundraising progress and thanked the board for a prior support letter.
Get email alerts on the Wawasee South topic
No spam. Unsubscribe anytime.
The executive director of Syracuse-Wawasee Trails updated the Kosciusko County Parks and Recreation Board on the Wawasee South trail project, describing current engineering work and fundraising partnerships for a 2.2-mile segment intended to improve school-to-school connections and safer routes for South Shore residents.
The director (name not provided in the meeting transcript) said engineering firm USI is conducting the engineering phase for an initial 1.2-mile section from Grandview to Ideal Beach and that the project has secured support from several local funders and foundations. "This little 2.2 mile section of trail...is the next level expansion for us because it's gonna provide, a school to school connection for our Syracuse, students and their families," the director said.
The director said the Wawasee South segment will eventually help connect to North Webster and the countywide Greenway network, and that an alternative, more scenic alignment exists but would be more expensive. The board's prior letter of support for the Wawasee South project was acknowledged; the director thanked the parks board and noted continued collaboration with the town of Syracuse and fundraising partners.
No additional county funding or formal action was requested at the meeting; the presentation was informational and the board indicated ongoing support.