Commissioners award installation contract for detention-center generator to ProBuilders
Summary
Bannock County staff recommended and commissioners approved awarding the installation portion of a detention-center diesel generator project to ProBuilders after rebidding procurement to separate purchase of the generator from installation.
Get email alerts on the Infrastructure Contracts topic
No spam. Unsubscribe anytime.
Bannock County commissioners on March 27 approved awarding the installation contract for a detention-center diesel generator to ProBuilders, county security and operations staff recommended.
Levi and county security staff explained the county originally budgeted approximately $315,000 to replace the generator and had planned to bundle purchase and installation. After staff restructured procurement to separately purchase the generator and competitively bid installation, staff procured a generator for about $100,000 and received ProBuilders’ installation bid of roughly $51,000, substantially reducing project cost compared with the original bundled estimate.
Why it matters: The procurement shift cut the county’s estimated cost for the generator replacement and installation roughly in half compared with the initial $315,000 planning figure, according to staff. Commissioners approved awarding the installation contract to ProBuilders by voice vote.
Staff noted there is a potential trade-in/credit value for the old generator; commissioners directed staff to address disposition and any trade-in credit as a separate matter. Notification letters associated with the procurement were provided for commissioner signatures.
The vote to award the contract was taken by voice vote; the motion carried with commissioners responding “aye.”