Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Brushy Creek utility authority hears progress on multimillion-dollar water projects; drought trigger highlighted

2787245 · March 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Authority staff reported schedule and budget updates on Phase 2 raw water delivery, Phase 1D treatment expansion and delivery-point improvements, and recommended extending the Phase 2A timeline to May 2028 as contractors cite regional congestion. Staff also reviewed drought forecasts and the intake-decommissioning trigger for Lake Travis.

Brushy Creek Regional Utility Authority members heard an update Wednesday on major water projects, from a $125 million Phase 2 raw-water delivery contract to the Phase 1D treatment-plant expansion, and were briefed on drought forecasts that could force changes to intake operations at Lake Travis.

Aaron Archer, a project engineer with Walker Partners, told the board the Phase 2 raw-water delivery contract is about 60% complete on a calendar-days basis and about 55% complete on a cost basis. He said contractors are working through a jointly reviewed recovery schedule and that recent iterations show the work trending back toward on-time completion. "The contractor has prepared a recovery schedule ... and it's working on weekends and additional work to bring the project up to speed," Archer said.

Archer reported work continues on an 8,800-foot cast-in-place concrete tunnel liner, pump-shaft casings (with one shaft left to drill and roughly three casings remaining to install and grout), and preparations for the pump-station building foundation. He said casing installation and grouting are expected to be complete around May under the current schedule.

On the Phase 1D water-treatment expansion, Archer said the authority issued a notice to proceed in May 2023 and the construction contract, valued at $17,000,000, ran past its original completion date. The contractor, Excel Construction, has submitted one change order for about $190,000; invoices to date total approximately $14,100,000 (about 83% of…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans